Construction of BOF shop No. 2
Contract on BOF shop No. 2 construction was concluded on the basis of Tender won in 05.08.1992 by the Consortium consisting VO “Tyazhpromexport”, Leader, “Gipromez”(Moscow), General Designer, “Azovmash” (Mariupol, Ukraine), equipment supplier, “Vostokmetallurgmontazh” (Chelyabinsk), equipment erection & adjustment contractor. Customer’s Consultant was M.N. Dastur & Co. (Kolkata).
Design capacity of BOF shop No.2 is 1.9 MT of steel per annum. Shop structure: 2 converters of 150 t capacity each, blowing system, gas cleaning plant, hot metal desulfurization plant, environment protection system and auxiliary facilities. Construction has been completed and Commissioning Certificate was signed on 01.09.1997.