Guarantee Test of Sinter Plant No 3

From March 14 to 17, 2016, a performance guarantee test was carried out at the Sinter Plant No. 3 of the Visakhapatnam Steel Plant in India, currently under construction by V/O “Tyazhpromexport” JSC, during which test following guaranteed performance indicators stipulated by the contract were achieved and exceeded:

 

Contractual value,
ton per day

Actual value,
ton per day

Daily output capacity

10,950

11,300

Maximum output capacity

13,140

13,186

The contract-stipulated values pertaining to quality of produced sinter, energy consumption figures, permissible atmospheric emissions and noise-emission level of the equipment have also been confirmed.